Information to develop a project network is collected from the
Choose correct answer/s
Organization breakdown structure.
Work breakdown structure.
Budget.
Project proposal.
Responsibility matrix.
Check answer
Question 2
Free
Multiple Choice
Which of the following represents an activity on an activity-on-node (AON)project network?
Choose correct answer/s
An arrow
A line
A node
Both an arrow and a line
An arrow, a line and a node all represent activities
Check answer
Question 3
Free
Multiple Choice
Arrows on an activity-on-node (AON)project network represent
Choose correct answer/s
An activity.
Project flow.
Dependency.
Project flow and dependency.
An activity and dependency.
Check answer
Question 4
Free
Multiple Choice
When translated into a project network, a work package will become
Choose correct answer/s
A single activity.
One or more activities.
A milestone.
A critical path.
An arrow.
Check answer
Question 5
Free
Multiple Choice
Which of the following is provided by both the project network and the work breakdown structure?
Choose correct answer/s
Dependencies
Sequencing
Interrelationships
Activity duration
Timing
Check answer
Question 6
Multiple Choice
On a project network, the activity times are derived from the
Choose correct answer/s
Organization breakdown structure.
Work packages.
Budget.
Project proposal.
Responsibility matrix.
To unlock the question
Question 7
Multiple Choice
Which of the following does NOT help describe a project network?
Choose correct answer/s
A graphic display of the flow and sequence of work through the project
Provides the basis for scheduling labor and equipment
Gives the times when activities can start and finish and when they can be delayed
Highlights major deliverables and identifies their completion dates
Identifies critical activities
To unlock the question
Question 8
Multiple Choice
An activity that has more than one dependency arrow flowing into it is termed a(n)
Choose correct answer/s
Parallel activity.
Critical path.
Burst activity.
Merge activity.
Independent activity.
To unlock the question
Question 9
Multiple Choice
The critical path in a project network is the
Choose correct answer/s
Shortest path through the network.
Longest path through the network.
Network path with the most difficult activities.
Network path using the most resources.
Network path with the most merge activities.
To unlock the question
Question 10
Multiple Choice
A(n) _________ activity has more than one dependency arrow flowing from it.
Choose correct answer/s
Parallel
Critical path
Burst
Merge
Independent
To unlock the question
Question 11
Multiple Choice
Which of the following can be used without coordinating with managers of succeeding activities?
Choose correct answer/s
Total slack
Free slack
Critical float
Float pad
Slip pad
To unlock the question
Question 12
Multiple Choice
Activities which can take place at the same time are termed
Choose correct answer/s
Parallel activity.
Critical path.
Burst activity.
Merge activity.
Independent activity.
To unlock the question
Question 13
Multiple Choice
A sequence of connected, dependent activities is termed a(n)
Choose correct answer/s
Path of events.
Parallel path.
Activity chain.
Path.
Dependent chain.
To unlock the question
Question 14
Multiple Choice
Bill is building a project network that involves testing a prototype.He must design the prototype (activity 1), build the prototype (activity 2), and test the prototype (activity 3).Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3.If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1.This is an example of
Choose correct answer/s
Conditional statements.
Looping.
Having more than one start node.
Good network development.
Natural network flow.
To unlock the question
Question 15
Multiple Choice
Which of the following is NOT one of the basic rules to follow when developing project networks?
Choose correct answer/s
An activity cannot begin until all preceding activities have been completed.
Each activity must have a unique identification number.
Conditional statements are allowed but looping statements are not allowed.
An activity identification number must be larger than that of any preceding activities.
Networks flow from left to right.
To unlock the question
Question 16
Multiple Choice
________ activities must be completed immediately before a particular activity.
Choose correct answer/s
Merge
Burst
Predecessor
Successor
Parallel
To unlock the question
Question 17
Multiple Choice
________ activities are to be completed immediately following a particular activity.
Choose correct answer/s
Merge
Burst
Predecessor
Successor
Parallel
To unlock the question
Question 18
Multiple Choice
The forward pass in project network calculations determines all of the following EXCEPT
Choose correct answer/s
Earliest time an activity can begin.
Earliest time an activity can finish.
Duration of the project.
The critical path.
How soon the project can finish.
To unlock the question
Question 19
Multiple Choice
The backward pass in project network calculations determines all of the following EXCEPT
Choose correct answer/s
Latest time an activity can begin.
Earliest time an activity can finish.
The critical path.
How long an activity can be delayed.
Latest time an activity can finish.
To unlock the question
Question 20
Multiple Choice
Which of the following correctly calculates the early finish for an activity?