Which of the following statements about projects and project management is NOT true?
Choose correct answer/s
A project is typically a one-time event.
Completing a project within budget is the most critical criterion for project success.
Projects are typically staffed with people from several different functional areas who may have more loyalty to their function than to the project.
None of the statements is true.
Check answer
Question 2
Free
Multiple Choice
Which of the following are factors affecting the success of a project?
Choose correct answer/s
Experience and authority of team members.
Equipment, facilities, and communications systems.
Organizational structure and reward systems.
All items are correct.
Check answer
Question 3
Free
Multiple Choice
Nearly all projects seem to go through the same phases and in the following sequence:
Choose correct answer/s
Planning, definition, execution, completion
Definition, planning, delivering, and closing
Definition, planning, execution, and completion
Selection, planning, delivering and completion
Check answer
Question 4
Free
Multiple Choice
Typically the resources required during a project's life are greatest in which stage of its life?
Choose correct answer/s
Planning
Definition
Completion
Execution
Check answer
Question 5
Free
Multiple Choice
What is a key factor that must be considered when an organization evaluates the potential of a project?
Choose correct answer/s
The project's fit with overall organizational strategy.
The availability of resources to execute the project.
The business justification for investing in the project.
All items are correct.
Check answer
Question 6
Multiple Choice
Zanda Corp.has decided that it needs a project team to implement a new ERP system.It wants the system implemented as soon as possible.Given this criterion, Zanda should choose a:
Choose correct answer/s
Matrix organizational structure.
Pure project structure.
Functional project structure.
Line and staff organization structure.
To unlock the question
Question 7
Multiple Choice
Colson Corp.has planned a simple project having four tasks.The task information for the project is shown below: What is the estimated completion time for the project?
Choose correct answer/s
29 days
25 days
22 days
19 days
To unlock the question
Question 8
Multiple Choice
Colson Corp.has planned a simple project having four tasks.The task information for the project is shown below: Does any task have slack? If so, how much?
Choose correct answer/s
None of the tasks have slack.
Task B has 3 days of slack.
Task C has 4 days of slack.
Task D has 2 days of slack.
Task C has 3 days of slack.
To unlock the question
Question 9
Multiple Choice
The network diagram below shows the five tasks required to complete a project and the associated times for those tasks. Which of the following identifies the critical path tasks?
Choose correct answer/s
A, B, D, F
A, B, C, D, E, F
A, B, E, F
A, C, E, F
To unlock the question
Question 10
Multiple Choice
The network diagram below shows the five tasks required to complete a project and the associated times for those tasks. What is the earliest completion of the project diagrammed?
Choose correct answer/s
23 weeks
24 weeks
28 weeks
37 weeks
To unlock the question
Question 11
Multiple Choice
The network diagram below shows the five tasks required to complete a project and the associated times for those tasks. What is the latest start date for task C?
Choose correct answer/s
2 weeks
7 weeks
6 weeks
5 weeks
To unlock the question
Question 12
Multiple Choice
The network diagram below shows the five tasks required to complete a project and the associated times for those tasks. Which task has the greatest amount of slack?
Choose correct answer/s
A
B
C
D
E
To unlock the question
Question 13
Multiple Choice
The forward pass in a critical path algorithm involves:
Choose correct answer/s
Calculating the late finish and late start for each task.
Calculating the late finish and the earliest possible start times for each task.
Calculating the earliest possible start and finish times for each task.
Calculating the earliest possible start and late start for each task.
To unlock the question
Question 14
Multiple Choice
"Crashing" in a project refers to:
Choose correct answer/s
Deciding to terminate a project.
Attempting to reduce the project scope.
Extending the deadline for completion of the project.
Speeding up an activity.
To unlock the question
Question 15
Multiple Choice
Joe Jones is a project manager on a major installation.He has been asked to provide weekly status reports on the project schedule.Joe should consider using which of the following:
Choose correct answer/s
Gantt chart
Crashing reports
WBS report
Network diagram
To unlock the question
Question 16
Multiple Choice
Why does project management often involve the management of conflict?
Choose correct answer/s
Projects often compete with routine operations and other projects for resources and personnel.
Project managers are under greater pressures than other managers in a firm.
Projects are often staffed with the personnel who have the least available expertise.
All items are correct.
To unlock the question
Question 17
Multiple Choice
Which of the following statements is true of projects?
Choose correct answer/s
Projects usually involve greater unknowns and uncertainty than repeated routine operations do.
Projects are usually more important than repeated routine operations.
Once a project plan is made, it is impossible to simultaneously improve the speed, quality, and cost of a project.
Technological factors are almost always more important than social factors in affecting project success.
To unlock the question
Question 18
Multiple Choice
A project manager usually has the greatest ability to affect social and technical success factors of a project in what stage of the project?
Choose correct answer/s
Planning
Execution
Completion
A project manager has equal ability to affect success factors across all stages.
To unlock the question
Question 19
Multiple Choice
The project organizational structure that provides the greatest balance between speed and efficiency is:
Choose correct answer/s
Matrix organizational structure.
Pure project structure.
Functional project structure.
Line and staff organization structure.
To unlock the question
Question 20
Multiple Choice
A primary advantage of a functional project organizational structure is:
Choose correct answer/s
The needs of the project client are prioritized over the needs of the function.
A single project manager has full control over the entire project.
A functional manager controls both the budget and the schedule.