Question 1
Free
Multiple Choice

A professional organization for project managers is the

Choose correct answer/s
A

PMI.

B

AMA.

C

MIS.

D

IPM.

E

PMBOK.

Check answer
Question 2
Free
Multiple Choice

Which of the following is NOT considered to be a characteristic of a project?

Choose correct answer/s
A

An established objective

B

A clear beginning and end

C

Specific time, cost and performance requirements

D

For internal use only

E

Something never been done by a particular company before

Check answer
Question 3
Free
Multiple Choice

Which of the following activities is NOT considered a project?

Choose correct answer/s
A

Developing a new software program

B

Designing a space station

C

Preparing the site for the Olympic Games

D

Production of automobile tires

E

Developing a new advertising program

Check answer
Question 4
Free
Multiple Choice

Which of the following activities is the best example of a project?

Choose correct answer/s
A

Processing insurance claims

B

Producing automobiles

C

Writing a policy manual

D

Monitoring product quality

E

Overseeing customer requests

Check answer
Question 5
Free
Multiple Choice

Which of the following is NOT one of the stages of a project life cycle?

Choose correct answer/s
A

Identifying

B

Defining

C

Planning

D

Executing

E

Closing

Check answer
Question 6
Multiple Choice

In the _____________ stage of What is a project?, project objectives are established, teams are formed, and major responsibilities are assigned.

Choose correct answer/s
A
Identifying
B
Defining
C
Planning
D
Executing
E
Closing
To unlock the question
Question 7
Multiple Choice

In the _____________ stage of What is a Project?, a major portion of the actual project work performed.

Choose correct answer/s
A
Identifying
B
Defining
C
Planning
D
Executing
E
Closing
To unlock the question
Question 8
Multiple Choice

In the _____________ stage of What is a Project? you are more likely to find status reports, changes, and the creation of forecasts.

Choose correct answer/s
A
Identifying
B
Defining
C
Planning
D
Executing
E
Closing
To unlock the question
Question 9
Multiple Choice

In the _____________ stage of What is a Project? the project's schedule and budget will be determined.

Choose correct answer/s
A
Identifying
B
Defining
C
Planning
D
Executing
E
Closing
To unlock the question
Question 10
Multiple Choice

In the _____________ stage of What is a Project? project the product is delivered to the customer and resources are released from the project.

Choose correct answer/s
A
Identifying
B
Defining
C
Planning
D
Executing
E
Closing
To unlock the question
Question 11
Multiple Choice

Which of the following is NOT typical of a project manager?

Choose correct answer/s
A
Managing a temporary activity
B
Overseeing existing operations
C
Managing a nonrepetitive activity
D
Responsible for time, cost and performance trade-offs
E
Work with a group of outsiders, including vendors and suppliers
To unlock the question
Question 12
Multiple Choice

Which of the following is NOT one of the driving forces behind the increasing demand for project management?

Choose correct answer/s
A
Compression of the product life cycle
B
Knowledge explosion
C
Increasing need for concurrent multi-project management
D
Declining need for product customization
E
More sustainable business practices
To unlock the question
Question 13
Multiple Choice

Project management is ideally suited for a business environment requiring all of the following EXCEPT

Choose correct answer/s
A
Accountability.
B
Flexibility.
C
Innovation.
D
Speed.
E
Repeatability.
To unlock the question
Question 14
Multiple Choice

Which dimension of project management centers on creating a temporary social system within a larger organizational environment that combines the talents of a divergent set of professionals working to complete the project?

Choose correct answer/s
A
Communication
B
Sociocultural
C
Social
D
Technical
E
Scheduling
To unlock the question
Question 15
Multiple Choice

Which of the following statements is true?

Choose correct answer/s
A
Project management is far from a standard way of doing business.
B
Project management is increasingly contributing to achieving organizational strategies.
C
Project management is being used at a consistent percentage of a firm's efforts.
D
Project management is a specialty that few organizations have access to.
E
All of these statements are false.
To unlock the question
Question 16
Multiple Choice

Project management is important to understand when people are a part of a project team because they

Choose correct answer/s
A
Work with others to create a schedule and budget.
B
Need to understand project priorities so they can make independent decisions.
C
Need to be able to monitor and report project progress.
D
Need to understand the project charter or scope statement that defines the objectives and parameters of the project.
E
All of these are reasons it is important for project team members to understand project management.
To unlock the question
Question 17
Multiple Choice

Project governance does NOT include

Choose correct answer/s
A
Setting standards for project selection.
B
Overseeing project management activities.
C
Centralization of project processes and practices.
D
Options for continuous improvement.
E
Allowing project managers to plan the project the way they see fit.
To unlock the question
Question 18
Multiple Choice

Projects should align with the organization's overall strategy in order to

Choose correct answer/s
A
Complete the project safely.
B
Reduce waste of scarce resources.
C
Ensure customer satisfaction.
D
Secure funding.
E
None of these are reasons why projects should align with the organization's overall strategy.
To unlock the question
Question 19
Multiple Choice

Two dimensions within the project management process are

Choose correct answer/s
A
Technical and sociocultural.
B
Cost and time.
C
Planned and unexpected.
D
Established and new.
E
Unique and reoccurring.
To unlock the question
Question 20
Multiple Choice

Which of these is NOT part of the "technical dimension" of project management?

Choose correct answer/s
A
WBS
B
Budgets
C
Problem solving
D
Schedules
E
Status reports
To unlock the question