A project has an initial cost of $27,400 and a market value of $32,600.What is the difference between these two values called?
Choose correct answer/s
net present value
internal return
payback value
profitability index
discounted payback
Check answer
Question 2
Free
Multiple Choice
Which one of the following methods of project analysis is defined as computing the value of a project based upon the present value of the project's anticipated cash flows?
Choose correct answer/s
constant dividend growth model
discounted cash flow valuation
average accounting return
expected earnings model
internal rate of return
Check answer
Question 3
Free
Multiple Choice
The length of time a firm must wait to recoup the money it has invested in a project is called the:
Choose correct answer/s
internal return period.
payback period.
profitability period.
discounted cash period.
valuation period.
Check answer
Question 4
Free
Multiple Choice
The length of time a firm must wait to recoup,in present value terms,the money it has in invested in a project is referred to as the:
Choose correct answer/s
net present value period.
internal return period.
payback period.
discounted profitability period.
discounted payback period.
Check answer
Question 5
Free
Multiple Choice
A project's average net income divided by its average book value is referred to as the project's average:
Choose correct answer/s
net present value.
internal rate of return.
accounting return.
profitability index.
payback period.
Check answer
Question 6
Multiple Choice
The internal rate of return is defined as the:
Choose correct answer/s
maximum rate of return a firm expects to earn on a project.
rate of return a project will generate if the project in financed solely with internal funds.
discount rate that equates the net cash inflows of a project to zero.
discount rate which causes the net present value of a project to equal zero.
discount rate that causes the profitability index for a project to equal zero.
To unlock the question
Question 7
Multiple Choice
You are viewing a graph that plots the NPVs of a project to various discount rates that could be applied to the project's cash flows.What is the name given to this graph?
Choose correct answer/s
project tract
projected risk profile
NPV profile
NPV route
present value sequence
To unlock the question
Question 8
Multiple Choice
There are two distinct discount rates at which a particular project will have a zero net present value.In this situation,the project is said to:
Choose correct answer/s
have two net present value profiles.
have operational ambiguity.
create a mutually exclusive investment decision.
produce multiple economies of scale.
have multiple rates of return.
To unlock the question
Question 9
Multiple Choice
If a firm accepts Project A it will not be feasible to also accept Project B because both projects would require the simultaneous and exclusive use of the same piece of machinery.These projects are considered to be:
Choose correct answer/s
independent.
interdependent.
mutually exclusive.
economically scaled.
operationally distinct.
To unlock the question
Question 10
Multiple Choice
The present value of an investment's future cash flows divided by the initial cost of the investment is called the:
Choose correct answer/s
net present value.
internal rate of return.
average accounting return.
profitability index.
profile period.
To unlock the question
Question 11
Multiple Choice
A project has a net present value of zero.Which one of the following best describes this project?
Choose correct answer/s
The project has a zero percent rate of return.
The project requires no initial cash investment.
The project has no cash flows.
The summation of all of the project's cash flows is zero.
The project's cash inflows equal its cash outflows in current dollar terms.
To unlock the question
Question 12
Multiple Choice
Which one of the following will decrease the net present value of a project?
Choose correct answer/s
increasing the value of each of the project's discounted cash inflows
moving each of the cash inflows forward to a sooner time period
decreasing the required discount rate
increasing the project's initial cost at time zero
increasing the amount of the final cash inflow
To unlock the question
Question 13
Multiple Choice
Which one of the following methods determines the amount of the change a proposed project will have on the value of a firm?
Choose correct answer/s
net present value
discounted payback
internal rate of return
profitability index
payback
To unlock the question
Question 14
Multiple Choice
If a project has a net present value equal to zero,then:
Choose correct answer/s
the total of the cash inflows must equal the initial cost of the project.
the project earns a return exactly equal to the discount rate.
a decrease in the project's initial cost will cause the project to have a negative NPV.
any delay in receiving the projected cash inflows will cause the project to have a positive NPV.
the project's PI must be also be equal to zero.
To unlock the question
Question 15
Multiple Choice
Rossiter Restaurants is analyzing a project that requires $180,000 of fixed assets.When the project ends,those assets are expected to have an aftertax salvage value of $45,000.How is the $45,000 salvage value handled when computing the net present value of the project?
Choose correct answer/s
reduction in the cash outflow at time zero
cash inflow in the final year of the project
cash inflow for the year following the final year of the project
cash inflow prorated over the life of the project
not included in the net present value
To unlock the question
Question 16
Multiple Choice
Which one of the following increases the net present value of a project?
Choose correct answer/s
an increase in the required rate of return
an increase in the initial capital requirement
a deferment of some cash inflows until a later year
an increase in the aftertax salvage value of the fixed assets
a reduction in the final cash inflow
To unlock the question
Question 17
Multiple Choice
Net present value:
Choose correct answer/s
is the best method of analyzing mutually exclusive projects.
is less useful than the internal rate of return when comparing different sized projects.
is the easiest method of evaluation for non-financial managers to use.
is less useful than the profitability index when comparing mutually exclusive projects.
is very similar in its methodology to the average accounting return.
To unlock the question
Question 18
Multiple Choice
Which one of the following is a project acceptance indicator given an independent project with investing type cash flows?
Choose correct answer/s
profitability index less than 1.0
project's internal rate of return less than the required return
discounted payback period greater than requirement
average accounting return that is less than the internal rate of return
modified internal rate of return that exceeds the required return
To unlock the question
Question 19
Multiple Choice
Why is payback often used as the sole method of analyzing a proposed small project?
Choose correct answer/s
Payback considers the time value of money.
All relevant cash flows are included in the payback analysis.
It is the only method where the benefits of the analysis outweigh the costs of that analysis.
Payback is the most desirable of the various financial methods of analysis.
Payback is focused on the long-term impact of a project.
To unlock the question
Question 20
Multiple Choice
Which of the following are advantages of the payback method of project analysis? I)works well for research and development projects II)liquidity bias III)ease of use IV)arbitrary cutoff point