Progress And Performance Measurement And Evaluation

This question bank verified by Studydeets
All Questions
Filter by:
Question 1
Free
Multiple Choice

A project monitoring system involves all of the following EXCEPT

Choose correct answer/s
A

Determining what data to collect.

B

Determining how, when, and who will collect the data.

C

Adjusting the data.

D

Analysis of the data.

E

Reporting current progress.

Check answer
Question 2
Free
Multiple Choice

Nancy tells her supervisor that as of right now, $1.05 worth of work has been accomplished for each $1 worth of scheduled work.Nancy got this information from viewing the

Choose correct answer/s
A

SV.

B

TCPI.

C

CPI.

D

SPI.

E

PCIB.

Check answer
Question 3
Free
Multiple Choice

Jessica just received the following information on her project: PV = 200, EV = 300, AC = 250, BAC = 1500, EAC = 1208.In terms of cost at completion.

Choose correct answer/s
A

The project will currently finish under budget.

B

The project will currently finish over budget.

C

The project will currently finish on budget.

D

The project will currently finish behind schedule.

E

There is insufficient information to draw conclusions.

Check answer
Question 4
Free
Multiple Choice

The first step in the project control process for measuring and evaluating project performance is to

Choose correct answer/s
A

Set a baseline plan.

B

Determine the project objectives.

C

Determine the project deliverables.

D

Analyze the project budget.

E

Review the project priority matrix.

Check answer
Question 5
Free
Multiple Choice

The second step in the project control process for measuring and evaluating project performance is to

Choose correct answer/s
A

Review the baseline plan with top management.

B

Analyze inputs to control system.

C

Compare plan against actual.

D

Measure progress and performance.

E

Review spending with team members.

Check answer
Question 6
Multiple Choice

The third step in the project control process for measuring and evaluating project performance is to

Choose correct answer/s
A
Review the baseline plan with top management.
B
Analyze inputs to the control system.
C
Compare the plan against actual performance.
D
Measure both progress and performance.
E
Review spending with team members.
To unlock the question
Question 7
Multiple Choice

The final step in the project control process for measuring and evaluating project performance is to

Choose correct answer/s
A
Take appropriate action.
B
Prepare a report to top management.
C
Follow up on corrective action.
D
Measure progress and performance.
E
Review spending with team members.
To unlock the question
Question 8
Multiple Choice

In monitoring project time (schedule)performance, actual performance should be compared to

Choose correct answer/s
A
Budgets for the current year.
B
Top management's targets.
C
Project network schedule derived from the WBS/OBS.
D
Progress on similar past projects.
E
Previous status reports.
To unlock the question
Question 9
Multiple Choice

A ___________ Gantt chart is a simple and effective way to depict progress on a project.

Choose correct answer/s
A
Baseline
B
Control
C
Variance
D
Tracking
E
Simple
To unlock the question
Question 10
Multiple Choice

A tool used to monitor past project schedule performance and current performance, and to estimate future schedule trends is a simple line chart known as a

Choose correct answer/s
A
Project control chart.
B
Gantt chart.
C
PERT chart.
D
Network diagram.
E
Milestone chart.
To unlock the question
Question 11
Multiple Choice

The earned value system starts with the time-phased costs that provide the project baseline, which is called the

Choose correct answer/s
A
Planned budgeted value of work scheduled.
B
Planned budgeted value of work completed.
C
Earned value of work scheduled.
D
Scheduled value of work scheduled.
E
Scheduled value of work completed.
To unlock the question
Question 12
Multiple Choice

The earned value of a project is the

Choose correct answer/s
A
Project cost to date adjusted for project scope changes.
B
Total project cost to date.
C
Cost incurred minus the planned cost.
D
Percent of the original budget that has been earned by actual work.
E
The planned time-phased baseline of the value of work scheduled.
To unlock the question
Question 13
Multiple Choice

The cost variance for a project is calculated by

Choose correct answer/s
A
EV - AC.
B
AC - SV.
C
PV - EV.
D
CV - EV.
E
EV - PV.
To unlock the question
Question 14
Multiple Choice

The schedule variance for a project is calculated by:

Choose correct answer/s
A
EV - AC
B
AC - SV
C
PV - EV
D
CV - EV
E
EV - PV
To unlock the question
Question 15
Multiple Choice

Baseline project budgets are derived from

Choose correct answer/s
A
The organization's overall budget.
B
Time-phasing the work packages.
C
Top management directions.
D
The total direct, direct project overhead and G&A overhead costs.
E
The earned value system.
To unlock the question
Question 16
Multiple Choice

Of the following costs, which are NOT included in baseline?

Choose correct answer/s
A
Suppliers
B
Equipment
C
Labor
D
Budget reserves
E
Contractors
To unlock the question
Question 17
Multiple Choice

When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the

Choose correct answer/s
A
0/100 percent rule.
B
Task complete rule.
C
Degree complete rule.
D
Work complete rule.
E
Percent complete rule.
To unlock the question
Question 18
Multiple Choice

Which performance index is the most potentially misleading?

Choose correct answer/s
A
CPI
B
EV
C
CV
D
SV
E
EAC
To unlock the question
Question 19
Multiple Choice

Which of the following are required to assess the current status of a project using the earned-value cost/schedule system?

Choose correct answer/s
A
BAC, EAC, and ETC
B
VAC, EAC, and BAC
C
CV, SV, and BAC
D
PV, EV, and AC
E
TCPI, EV, and PV
To unlock the question
Question 20
Multiple Choice

Which of the following methods of variance analysis is the best indicator of how far off the budget a project will be at completion?

Choose correct answer/s
A
BAC
B
EAC
C
ETC
D
VAC
E
TCPI
To unlock the question