Project Planning And Scheduling

This question bank verified by Studydeets
All Questions
Filter by:
Question 1
Free
Multiple Choice

The purpose of performing a forward pass is to

Choose correct answer/s
A

identify the critical path.

B

determine the early start and the early finish times.

C

determine the late start and the late finish times.

D

determine the slack available in the process.

Check answer
Question 2
Free
Multiple Choice

Multiple critical paths can exist under the critical path method (CPM)because

Choose correct answer/s
A

there is more than one way to complete the project.

B

different network paths can have the same total time.

C

great flexibility of activity sequences is available.

D

none of the above.

Check answer
Question 3
Free
Multiple Choice

Project management requires

Choose correct answer/s
A

scheduling, planning, and controlling.

B

analytic skills.

C

behavioral skills.

D

all of the above.

Check answer
Question 4
Free
Multiple Choice

Gantt charts are effective for project scheduling if

Choose correct answer/s
A

activities are highly interconnected.

B

activity times are random.

C

the project contains simple activity sequences.

D

all of the above.

Check answer
Question 5
Free
Multiple Choice

Which of the following is NOT included in project control?

Choose correct answer/s
A

Monitoring costs, time, and performance.

B

Adhering to the budget.

C

Correcting the plan as necessary.

D

All of the above are included.

Check answer
Question 6
Multiple Choice

Which of the following statements is true about a critical path?

Choose correct answer/s
A
It consists of activities for which early start time equals late start time.
B
The total time of activities on the path take the longest time.
C
There is no slack in the activities along the critical path.
D
All of the above.
To unlock the question
Question 7
Multiple Choice

The critical path of the following network is image

Choose correct answer/s
A
1-3-4-5
B
2-3-4-5
C
2-3-5
D
more than one of the above.
To unlock the question
Question 8
Multiple Choice

A forward pass of the above network (problem 8)indicates that the early start time of activities 4-5 is

Choose correct answer/s
A
4.
B
5.
C
3.
D
none of the above.
To unlock the question
Question 9
Multiple Choice

The advantage(s)of the network method over the Gantt chart is (are)

Choose correct answer/s
A
the network method is easy to use and quite widely understood.
B
the network method shows precedence relationships more explicitly than Gantt charts.
C
network methods are less costly to use.
D
all of the above.
To unlock the question
Question 10
Multiple Choice

"Slack" refers to the difference between

Choose correct answer/s
A
late and early times.
B
finish and start times.
C
observed and predicted times.
D
optimistic and pessimistic times.
To unlock the question
Question 11
Multiple Choice

The longest series of connections in the project network from the start to the end of the activities is also referred to as

Choose correct answer/s
A
the action path.
B
the critical path.
C
the master schedule.
D
float or slack.
To unlock the question
Question 12
Multiple Choice

Which of the following statements is NOT correct about Gantt charts?

Choose correct answer/s
A
Gantt charts are extremely easy to use and are quite well understood.
B
Gantt charts show not only the time required for an activity but also the time at which a particular activity takes place.
C
Gantt charts show the interdependencies and relationships between activities.
D
Gantt charts can also be used while scheduling service operations.
To unlock the question
Question 13
Multiple Choice

Which of the following is true for a critical activity?

Choose correct answer/s
A
ES = EF
B
EF = LS
C
LF = LS
D
ES = LS
To unlock the question
Question 14
Multiple Choice

Consider the following definitions of slack: #1 LS - ES
#2 LF - EF

Choose correct answer/s
A
Only #1 is correct.
B
Only #2 is correct.
C
Both definitions are correct.
D
Neither definitions are correct.
To unlock the question
Question 15
Multiple Choice

What is the expected completion time of the project?

Choose correct answer/s
A
11
B
12
C
13
D
15
To unlock the question
Question 16
Multiple Choice

What is the critical path of the network,given the information above?

Choose correct answer/s
A
A-B-C-D.
B
A-B-D.
C
A-C-D.
D
Not enough information is provided.
To unlock the question
Question 17
Multiple Choice

What is the normal project completion time,given the information above?

Choose correct answer/s
A
11
B
13
C
14
D
16
To unlock the question
Question 18
Multiple Choice

Given the information above,what is the LS time for activity B?

Choose correct answer/s
A
5
B
7
C
9
D
11
To unlock the question
Question 19
Multiple Choice

Given the information above,what is the project cost if the project is crashed by one day?

Choose correct answer/s
A
$125
B
$250
C
$270
D
None of the above.
To unlock the question
Question 20
Multiple Choice

Given the information above,what is the project cost if the project is crashed by two days?

Choose correct answer/s
A
$250
B
$295
C
$500
D
None of the above.
To unlock the question