Without any formal planning, the president of a software company remarks in a speech that new technologically advanced software will be available in one year.This may lead to a project that must be done faster than anticipated.This is an example of reducing project duration caused by
Choose correct answer/s
Imposed project deadlines.
Time to market.
Unforeseen project delays.
High overhead.
Incentive contracts.
Check answer
Question 2
Free
Multiple Choice
Intense global competition and rapid technological advances create pressure to develop projects rapidly.This is an example of reducing project duration caused by
Choose correct answer/s
Imposed project deadlines.
Time to market.
Unforeseen project delays.
High overhead.
Incentive contracts.
Check answer
Question 3
Free
Multiple Choice
A contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion.This is an example of reducing project duration caused by
Choose correct answer/s
Imposed project deadlines.
Time to market.
Unforeseen project delays.
High overhead.
Incentive contracts.
Check answer
Question 4
Free
Multiple Choice
Adverse weather, design flaws, and equipment breakdown can create negative slack.This is an example of reducing project duration caused by
Choose correct answer/s
Imposed project deadlines.
Time to market.
Unforeseen project delays.
High overhead.
Incentive contracts.
Check answer
Question 5
Free
Multiple Choice
In a Project Cost-Duration Graph, total project costs are a sum of
Choose correct answer/s
Labor, material and equipment costs.
Direct costs plus interest.
Direct labor costs and the project manager's salary.
Direct costs and the project manager's salary.
Direct and indirect costs.
Check answer
Question 6
Multiple Choice
Which of the following is NOT considered a project indirect cost?
Choose correct answer/s
Supervision
Consultants
Equipment
Interest
The project manager's salary
To unlock the question
Question 7
Multiple Choice
As a project is crashed and project duration is reduced, indirect costs typically
Choose correct answer/s
Increase.
Become unstable.
Decrease.
Become unreliable.
Stay the same.
To unlock the question
Question 8
Multiple Choice
Before crashing, direct costs for an activity represent normal costs, which typically mean low-cost, efficient methods for completing the activity in a(n) ________ amount of time.
Choose correct answer/s
Normal
Budgeted
Optimized
Expected
Targeted
To unlock the question
Question 9
Multiple Choice
The shortest possible time an activity can be completed realistically is called ___ _____ time.
Choose correct answer/s
Expedited
Accelerated
Crash
Optimistic
Optimal
To unlock the question
Question 10
Multiple Choice
As a project is crashed and project duration is reduced, direct costs typically
Choose correct answer/s
Increase.
Become unstable.
Decrease.
Become unreliable.
Stay the same.
To unlock the question
Question 11
Multiple Choice
The direct cost for completing an activity in the shortest time it can realistically be completed in is called its __________ cost.
Choose correct answer/s
Normal
Reserve
Crash
Accelerated
Expedited
To unlock the question
Question 12
Multiple Choice
An activity's crash cost includes ________ costs.
Choose correct answer/s
Direct
Indirect
Overhead
Total
Normal
To unlock the question
Question 13
Multiple Choice
Cost slope can be determined by dividing the
Choose correct answer/s
Run by the rise.
Rise by the run.
Crash cost by the normal cost.
Normal cost by the crash cost.
Indirect cost by direct cost.
To unlock the question
Question 14
Multiple Choice
The less steep the cost slope of an activity, the
Choose correct answer/s
Less it costs to shorten one time period.
More it costs to shorten one time period.
Smaller the crash time is.
Larger the crash time is.
Cannot be determined by the information given.
To unlock the question
Question 15
Multiple Choice
Which of the following correctly calculates an activity's cost slope?
Choose correct answer/s
(normal cost - crash cost)/(normal time - crash time)
(crash cost - normal cost)/(normal time - crash time)
(normal time - crash time)/(crash cost - normal cost)
(normal time - crash time)/(normal cost - crash cost)
(crash cost - normal cost)/(crash time - normal time)
To unlock the question
Question 16
Multiple Choice
Emily has recently learned that she needs to reduce the duration of her project to meet an imposed deadline.She has calculated the crash cost per unit and knows the maximum units each activity can be reduced.What is the next step?
Choose correct answer/s
Find the activity with the lowest crash cost
Calculate the optimum cost-time point
Calculate the crash point
Identify the critical path
Find the activity with the highest crash cost
To unlock the question
Question 17
Multiple Choice
In selecting the best activity to crash you would first select the activity with the
Choose correct answer/s
Earliest start time.
Most steep slope.
Least steep slope.
Longest duration.
Largest crash time.
To unlock the question
Question 18
Multiple Choice
When reducing project duration, the duration for a project that is optimal is at the point where
Choose correct answer/s
Direct costs are the lowest.
Indirect costs are the lowest.
Direct costs equal indirect costs.
Total project costs are the lowest.
The project changes from time-constrained to resource-constrained.
To unlock the question
Question 19
Multiple Choice
When reducing project duration, the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known.After this, the critical path must be identified.What is the next step?
Choose correct answer/s
Find the activity with the lowest crash cost
Calculate the optimum cost-time point
Calculate the crash point
Calculate indirect cost per time unit
Find the activity with the steepest cost slope
To unlock the question
Question 20
Multiple Choice
When determining which activity to crash, there are other factors that should be assessed beyond cost.Which of the following is NOT one of these factors?
Choose correct answer/s
The inherent risk associated with the activity
How crashing will impact the morale and motivation of the individuals working on that activity
Resource availability after crashing that activity
The level of difficulty involved in completing the activity