Scheduling Resources And Costs

This question bank verified by Studydeets
All Questions
Filter by:
Question 1
Free
Multiple Choice

Resources are adequate, but demand varies widely over the life of the project.Delaying noncritical activities to lower peak demand on resources is known as resource

Choose correct answer/s
A

Shifting.

B

Effectiveness.

C

Manipulating.

D

Smoothing.

E

Allocation.

Check answer
Question 2
Free
Multiple Choice

If resources are not adequate to meet peak demands, the resulting reschedule is termed

Choose correct answer/s
A

Resource-constrained scheduling.

B

Time-constrained scheduling.

C

Mandatory leveling.

D

Project resource adjustment.

E

Allocation.

Check answer
Question 3
Free
Multiple Choice

Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation?

Choose correct answer/s
A

Activity delays

B

Project delays

C

Difficulty in taking quick corrective action

D

Increase costs

E

Scope creep

Check answer
Question 4
Free
Multiple Choice

When developing a new software package, logically, the software must be designed before the code is written, and the code must be written before it is tested.These activities are dependent on each other by _________ constraints.

Choose correct answer/s
A

Physical

B

Technical

C

Resource

D

Schedule

E

Time

Check answer
Question 5
Free
Multiple Choice

When considering the sequence and timing of activities, which of the following is NOT one of the types of project network constraints?

Choose correct answer/s
A

Physical

B

Technical

C

Resource

D

Time

E

All of these are types of constraints that could impact structure of the project network.

Check answer
Question 6
Multiple Choice

Sam, the project engineer, has been scheduled to run the product system test at the same time he is to build a marketing prototype.This is an example of what type of resource constraint?

Choose correct answer/s
A
Physical
B
Technical
C
People
D
Equipment
E
Time
To unlock the question
Question 7
Multiple Choice

Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test.This is an example of a constraint that could impact the sequence and timing of activities in a project network.What type of constraint is it?

Choose correct answer/s
A
Physical
B
Technical
C
Resource
D
Scheduling
E
Time
To unlock the question
Question 8
Multiple Choice

All of the following are types of resource constraints EXCEPT

Choose correct answer/s
A
Materials.
B
People.
C
Equipment.
D
Information.
E
Human.
To unlock the question
Question 9
Multiple Choice

Gene is trying to order the concrete needed to continue his project.However, the supplier will not be able to deliver it until next week.This is an example of what kind of resource constraint?

Choose correct answer/s
A
Working capital
B
People
C
Equipment
D
Information
E
Materials
To unlock the question
Question 10
Multiple Choice

A special truck that George needs on his project has been scheduled on another project.This is an example of what type of resource constraint?

Choose correct answer/s
A
Working capital
B
People
C
Equipment
D
Information
E
Materials
To unlock the question
Question 11
Multiple Choice

Most of the scheduling methods available today require the project manager to classify the project as either _______ constrained or ______ constrained.

Choose correct answer/s
A
Time, quality
B
Quality, resource
C
Cost, time
D
Quality, cost
E
Time, resource
To unlock the question
Question 12
Multiple Choice

Regina's boss has told her that her project is very important.If the critical path is delayed, she will be given whatever she needs to get it back on schedule.Her project is classified as ________ constrained.

Choose correct answer/s
A
Time
B
Quality
C
Cost
D
Performance
E
Resource
To unlock the question
Question 13
Multiple Choice

In reviewing the status of her project with top management, Shirley was told that there are only two programmers that she can use for her project.Her project is classified as __________ constrained.

Choose correct answer/s
A
Time
B
Quality
C
Cost
D
Performance
E
Resource
To unlock the question
Question 14
Multiple Choice

All resource leveling techniques involve

Choose correct answer/s
A
Delaying noncritical activities.
B
Delaying critical activities.
C
Using negative slack.
D
Delaying the project.
E
Adding resources.
To unlock the question
Question 15
Multiple Choice

Technical constraints have been carefully considered when developing a project network.Which of the following is true at this point?

Choose correct answer/s
A
Resources have been assigned to each activity so they are adequate to complete the project on time.
B
Technical dependencies between activities are known.
C
The project completion date can be established.
D
The project is ready to be implemented.
E
All of these are true statements once technical constraints have been established.
To unlock the question
Question 16
Multiple Choice

Rachel is working on a project that technically allows three activities to be done at the same time.If they were to be implemented at the same time, she would need 5 contractors in order for the activities to be completed on time.There are only 3 available for her to use.This is an example of what type of constraint?

Choose correct answer/s
A
Technical
B
People
C
Equipment
D
Physical
E
Materials
To unlock the question
Question 17
Multiple Choice

Resource leveling or smoothing can have all the following results on a project EXCEPT

Choose correct answer/s
A
Lower peak resource demand.
B
Reduced resource need over the life of the project.
C
Reduced fluctuations in resource demand.
D
A longer project duration.
E
A more sensitive network.
To unlock the question
Question 18
Multiple Choice

Jan is trying to reallocate resources in a time-constrained project to create smoother resource utilization.She should first identify activities with the

Choose correct answer/s
A
Smallest duration.
B
Least slack.
C
Most slack.
D
Lowest identification number.
E
Highest cost.
To unlock the question
Question 19
Multiple Choice

In a resource-constrained project, which of the following is most likely to be changed?

Choose correct answer/s
A
The completion date
B
The budget
C
Project quality
D
Resource levels
E
Scope creep
To unlock the question
Question 20
Multiple Choice

In a resource-constrained project, the first priority in assigning resources is usually given to activities with the

Choose correct answer/s
A
Smallest duration.
B
Least slack.
C
Most slack.
D
Lowest identification number.
E
Highest cost.
To unlock the question